The Office for Nuclear Regulation (ONR) has informed Westinghouse that it has agreed to close a ‘regulatory issue’ raised against its AP1000 reactor design. The regulatory issue, opened in February 2010 by ONR’s predecessor organisation (HSE’s Nuclear Directorate) concerned the AP1000’s civil structures, which were assessed by the regulator as part of the Generic Design Assessment, run jointly by ONR and the Environment Agency.
ONR has judged that although there are still design issues with the civil structures, progress made by the company means that these are now less significant and the regulator is confident that Westinghouse will be able to resolve them satisfactorily before final ‘design acceptance confirmation’ is granted. More information can be found on the joint regulator’s website for new nuclear power stations.