Chapelcross defuelling project hits milestone

Author: Admin - Categories: Chapelcross, Magnox, NII - Tags: , ,

Magnox NorthMagnox North Chapelcross’s decommissioning programme hit a significant milestone this week as the 50th Flask was safely shipped to the Sellafield Site in Cumbria for reprocessing.

 

Following formal permission to start defuelling from the Nuclear Installations Inspectorate (NII) in July 2009, and the first element being removed from the reactor core just over a year ago on Monday 18th August 2009 there has been consistent progress made with the defuelling programme at the Chapelcross Site. Read it all..

Share
March 24, 2010

Hazard is removed as last drum of uranium leaves Chapelcross

Author: Admin - Categories: Chapelcross, Magnox, NDA - Tags: , , , ,
chapelcross-mdu-truck400x300NDA Press Release

The last of more than 10,000 drums of Magnox Depleted Uranium (MDU) left Chapelcross this week, signifying the reduction of a major hazard associated with the UK’s civil nuclear legacy. Read it all..

Share
September 8, 2009

Chapelcross Starts Defuelling from Two Reactors

Author: Admin - Categories: Chapelcross, Magnox - Tags: , ,

magnox north 090812Another key milestone in the defuelling of the four Chapelcross Reactors was reached on Thursday 3 September when defuelling started  on Reactor 3.  Read it all..

Share
July 8, 2009

NDA Supports Study into Solway Energy Gateway

Author: Admin - Categories: Chapelcross, NDA, decommissioning, sellafield - Tags: , , ,

NDA Press release 6th Julysolway225x165[1]

Together with the Northwest Regional Development Agency (NWDA) and Scottish Enterprise we have agreed to commission a £100,000 feasibility study to evaluate options for harnessing Tidal Energy on the Solway Firth. Read it all..

Share
April 6, 2009

First Flask of Fuel Leaves Chapelcross

Author: Admin - Categories: Chapelcross, sellafield - Tags: ,

fuel-flaskMagnox North News

A major milestone in the defuelling of the four Chapelcross Reactors was reached this week when the first M2 flask of fuel containing 116 elements left the site for reprocessing at Sellafield. Read it all..

Share
February 6, 2009

NDA £2.5 Million Business Boost To Chapelcross

Author: Admin - Categories: Chapelcross, NDA - Tags: , ,

chapelcrossNDA News 06 February 2009

The NDA’s Socio-Economic Committee has agreed an investment totalling £2.5 million for two projects to develop an Industrial Park and Business Incubation Centre at Chapelcross. Read it all..

Share
September 11, 2008

First fuel elements removed from Chapelcross reactors

Author: Admin - Categories: Chapelcross - Tags: , , ,

31 August 2008

Magnox North’s Chapelcross site began the next phase in its life this week when final de-fuelling of Reactor 1 commenced.

The first fuel element was removed from the reactor core on Monday 18th August, beginning the active commissioning of the newly upgraded fuel route. Approximately 40,000 fuel elements will be systematically removed from all four reactors and dispatched for reprocessing at Sellafield Site in Cumbria. Read it all..

Share